18th St. Water Line

This project involves replacing an existing 1944, oversized, cast-iron, 15-inch water line in 18th Street, between Waco Drive and Bosque Boulevard.  This water line replacement project is being done in coordination with an upcoming street overlay project.  The line was previously identified for replacement due to numerous documented line breaks and the difficulty in obtaining repair parts.  The project will also replace any connecting water lines to a point just outside of the upcoming street pavement project.

Projected Start/End Dates

Work on this project is anticipated to begin in Summer 2022 and is estimated to be complete in Winter 2023.

Projected Cost

Approximately $1.7 million

Anticipated Impact to Residents

Traffic on 18th St. will be impacted, by shifting lane closures, between Waco Dr. and Bosque Blvd. as work proceeds.

Primary Core Issue Addressed

Water Master Plan: Asset renewal