Brazos River Embankment Repair

Over years, the flow of the river has eroded the bank near and around the outfall area of the WMARSS Central Treatment Plant, endangering the outfall structure and operations at the plant. This project involves, working with the U.S. Army Corps of Engineers to reestablish the bank by placement of riprap, protecting the bank from erosion.

Projected Start/End Dates

Work on this project began in Fall 2021 and anticipated to be complete in Summer 2023.

Projected Cost

Approximately $9 million

Anticipated Impact to Residents

At this time, no disruptions or street closures are anticipated as a result of this project.

Primary Core Issue Addressed

Wastewater Master Plan: Asset renewal