This project involves the relocation and replacement of wastewater mains in the area of Crestwood Drive, Lake Oaks Drive, and Lockwood Drive. Many of the existing wastewater mains are located in ravines. Rain events and poor soil conditions have caused hill slides in the past several years. These erosive conditions have exposed sewer piping and joints, and compromised aerial crossings of the ravine drainage ways, causing many leaks and repairs in this area.

Projected Start/End Dates

Work on this project began in November 2020 and is estimated to be complete in February 2022.

Projected Cost

Approximately $3.2 million

Anticipated Impact to Residents

Heavy machinery parking overnight and noise are potential impacts of this project to residents.

Primary Core Issue Addressed

Wastewater Master Plan: Asset renewal