Gurley Lane Wastewater Improvements

4,530 ft of 48” wastewater line from the new Transfer Lift Station, across University Parks Dr., along Gurley Lane, southwest to 4th St. 

Projected Start/End Dates

Work on this project began in Fall 2020 and is estimated to be complete in Summer 2023.

Projected Cost

Estimated approximately $5.7 million

Anticipated Impact to Residents

Traffic will be impacted along Gurley Lane between University Parks Dr. and S. 4th St.

Primary Core Issue Addressed

Wastewater Master Plan: Asset renewal