A new water line will be constructed and connected to an existing water line to establish a new water line loop for this area of the city. This will improve the efficiency of the water distribution system and improve water quality.
Projected Start/End Dates
This project is currently in progress.
Projected Cost
Approximately $250,000
Anticipated Impact to Residents
We anticipate some street closures due to this project.
Primary Core Issue Addressed
Water Master Plan: Transmission