Mt. Carmel Water Treatment Plant Improvements

This project involves multiple improvements and repairs needed at the plant, including the replacement of water treatment valves, repair of concrete basin walkways, installation of new safety handrails, removal of unused flocculation equipment and antiquated chemical feed equipment, installation of automatic valve actuators, and upgrades to the chemical feed system.

Projected Start/End Dates

Work on this project began in Fall 2018 and is expected to be completed in Winter 2023.

Projected Cost

Approximately $5.5 million

Anticipated Impact to Residents

At this time, no disruptions or street closures are anticipated as a result of this project.

Primary Core Issue Addressed

Water Master Plan: Asset renewal